The agency's
scientists had waited too long for this moment. Galileo's parade would
not be rained on by a bunch of peaceniks.
The launch was already running late as it was--almost seven years
late. Congress gave the Galileo project its stamp of approval way back
in 1977 and the probe, which had been budgeted to cost about $400
million, was scheduled to be launched in 1982. However, things began
going wrong almost from the start.
In 1979, NASA pushed the flight out to 1984 because of shuttle
development problems. Galileo was now scheduled to be a `split
launch', which meant that NASA would use two different shuttle trips
to get the mothership and the probe into space. By 1981, with costs
spiralling upwards, NASA made major changes to the project. It stopped
work on Galileo's planned three-stage booster system in favour of a
different system and pushed out the launch deadline yet again, this
time to 1985. After a federal Budget cut fight in 1981 to save
Galileo's booster development program, NASA moved the launch yet
again, to May 1986. The 1986 Challenger disaster, however, saw NASA
change Galileo's booster system for safety reasons, resulting in
yet more delays.